§ 117.687. Missouri River.
74 words·~1 min read·
/us/cfr/t33/s§ 117.687·A research copy — for the controlling text, always check the official state or federal source. Not legal advice.
The draws of the bridges, except for the Atchison Railroad Bridge, Mile 422.5, see § 117.411(b) for further details, across the Missouri River shall open on signal; except during the winter season between the date of closure and date of opening of the commercial navigation season as published by the Army Corps of Engineers, the draws need not open unless at least 24-hours advance notice is given. \[USCG-2014-0358, 80 FR 81181, Dec. 29, 2015\]
Connections5 cite this
Citation graph
cites case law
§ 117.687
Missouri River.
Fed. Reg.×5
Cites 0Cited by 5 across 1 source